Goldenseal Construction Estimating Software |
| Assembly
name-- In Goldenseal Estimating Software |
add for 6 mil poly
|
| Construction
Category |
SubCategory |
| Concrete |
Concrete xxx |
| Construction ITEM DESCRIPTION |
Concrete estimating unit cost for application
of a 6 mil polyethylene vapor barrier under a concrete slab.
|
| Unit Size |
One square foot.
|
| Labor
Costs |
We figure one unskilled hour per 200
square feet of area.
|
| Material
Costs |
One square foot of polyethylene sheeting,
with a 10% waste factor for loss and overlap.
|
| Hard Construction Costs, Typical |
$.14 per square foot of concrete
slab area
|
| Suggested
Quantity |
Floor slab area.
|
| Source
of Construction Pricing |
Based on crew timing on a few basement
remodeling projects done by Turtle Creek
Construction.
|
| Places Included |
Architect Starter File, Construction
Starter File, Developer Starter File
|
Click here for more about Goldenseal construction estimating software.